Historic Firestone Waterline Project
On Wednesday night, in two separate actions, the Board of Trustees approved contracts for the Historic Firestone Waterline Replacement Project #2.
The first is a contract with Defalco Construction Co. for the construction work of the project. The projects approved in this contract include:
- Waterline installation and surface improvements on 4th Street between Buchannan Avenue and Granville Avenue, Buchannan Avenue and Granville Avenue between 4th Street and 3rd Street
- Waterline installation and surface improvements on Wooster Drive
- 3rd Street surface improvements between Granville Avenue and Buchannan Avenue
- Jackson Drive surface improvements
These areas were selected for Project #2 due to roadway condition, waterline condition, constructability, and overall cost.
The second contract is for construction management of the Firestone Waterline Replacement Project #2 by Ditesco. Ditesco worked as the design engineer on the project and submitted a proposal for construction management to assist the Town during construction.
Work on the projects listed above is expected to begin in May. The contractor will deliver door hangers to impacted properties notifying them of upcoming work near them. In addition, the Town will send out notifications to the public with additional details and specific timing.